Text Box: Consumers Energy Co.
West Olive, Michigan
Engineering Fees  $75,000

Project Overview

New environmental regulations were requiring buried fuel oil piping to be taken out of service and replaced with above ground piping.  The project was done in phases in order to limit the time the facility was without fuel oil.  Century A&E performed field verification of existing drawings, modification to existing piping and instrument diagrams (P&IDs), pump sizing and specification, piping drawings, hanger details, structural modifications, pipe bridge design and power and instrument wiring diagrams.

 

Services Provided

Piping Design, Structural Engineering and Instrumentation, Power & Controls

Underground Fuel Oil Piping Replacement