WASTEWATER TREATMENT PLANT EXPANSION

Project Overview

Engineering and construction support services were provided during the construction phase of the upgrades to the Coldwater, Michigan treatment plant.  The 2.7 million gallon per day treatment plant was increased to 3.2 million gallons a day.  A new SCADA system, instrumentation and the latest water treatment technology were incorporated into the design.  Design services included modifications to control systems, instrumentation, and modifying the original design to meet actual field conditions.  Construction support included the contractor’s RFI’s, site inspections, on-site evaluation of construction issues, and start-up support.

 

Services Provided

Electrical Engineering and Construction Services

Text Box: City of Coldwater, Michigan
(In conjunction with Williams & Works)
Spring 2001
Project Cost:  $3.8 Million